NEWLY ENACTED PRE-LITIGATION REQUISITES:
CALIFORNIA CIVIL CODE §1375
A. Prior to filing of suit for construction defects, the associations
must:
1. Submit formal written notice to developer/builder of damage claims.
2. Contents of notice must contain the following itemizations:
a. preliminary list of construction defects thus far identified,
b. summary of homeowner questionnaires stating the nature and extent of
any alleged defects,
c. summary of findings gleaned from testing results,
d. all costs incurred in generating this information is borne by the association.
B. Developer/Builder Duties and Options
1. Developer/Builder has twenty-five (25) days following receipt of
association's notice to request meet and confer with associations board
of directors.
2. Topics to be discussed are limited to:
a. determining the nature and extent of preliminary defects claimed,
b. proposals for method of repair,
c. proposals to submit claims to alternative dispute resolution,
d. to define the scope of any request from developer/builder to inspect
premises and common areas and to conduct own testing.
3. If developer/builder requests a meet and confer, it must simultaneously
inform and notice its insurance providers of the pending claim. This notice
to the insurance activates its legal obligation to the developer pursuant
to the terms of its policies, primarily that of funding a defense. (See
Also, Montorse Chemical Corp. v. Admiral Insurance Co. 10 CAL 4th 645)
4. Procedural steps then accelerate:
a. Within thirty (30) days of the initial meet and confer, or completion
of inspections and/or testing, developer/builder must again request a second
meet and confer with board of directors,
b. Developer/builder must submit to the board of directors the following:
(1) a written settlement offer,
(2) concise explanations justifying the terms of this offer,
(3) any offer to submit its contentious to alternative dispute resolution
proceedings,
(4) statement of adequate funds to satisfy conditions contained in settlement
offer,
(5) a summary of its test results as to nature and extent of defects, if
the association declined to perform its own initial testing.
(6) Should developer/builder fail to timely submit items required, the
association is relieved of any further obligation to satisfy pre-litigation
requisites.
5. No less than ten (10) days after submittal of developer/builder proposals,
the board of directors and developer/builder must again meet and confer
about the settlement proposals advance.
C. Should board of directors reject the settlement package proposed
by developer/builder, the board must either:
1. Set up and conduct another meeting open to each member of the association,
no less than fifteen (15) days prior to filing a lawsuit (do not know what
this is),
2. No less than fifteen (15) days before said meeting, written notice must
be sent to each member specifying all of the following:
a. the purpose of the meeting is to discuss obligations and costs of
filing a lawsuit (See AB 463 Goldsmith Bill),
b. discussion of any options available in lieu of suit,
c. the complete text of the developer/builder1s settlement proposals,
d. the preliminary list of defects provided by the association to developer/builder,
in addition to any other documentation initially provided by the association,
e. a statement informing the members that the developer/builder is paying
for all expenses incurred with the sending of the above documents and proposals,
in addition to paying three dollars ($3) per member to hold the meeting,
f. any and all contents utilized and/or verbalized at this meeting are
privileged and inadmissible as evidence in any subsequent legal proceeding
unless agreed to by the association.
D. Alternatively, should the builder, at any time, fail to satisfy
all the previously set forth requisites, the association may file its lawsuit
thirty (30) days following written notice sent to each member. The notice
must contain:
1. the preliminary list of defects initially provided to the developer/builder,
including any other documents so provided,
2. information on where and when association members may inspect these
documents,
3. all the options available to adequately address the construction deficiencies
throughout the development,
4. a statement that if five (5%) percent of the member request a special
meeting within fifteen (15) days of this notice's mailing or hand delivery
to each, another meeting of the membership must be held, unless the CC%R's
provide for a different procedure,
5. Compliance with above alternatives, following the refection of settlement
proposals, will excuse the association from satisfying the conditions set
forth in Civil Code §1368.4 (the newly enacted Goldsmith Bill,
AB 463). NOTE: Any and all time guidelines following the initial notice
may be modified by the mutual agreement of the association and the developer/builder.
E. In the event of substantial noncompliance with the prerequisites:
1. Should the association fail to comply with the procedural prerequisites
of the legislation, the developer/builder has ninety (90) days after their
answer to the complaint (suit) has been served (not filed) to seek judicial
relief.
2. Failure to meet this time table results in a waiver of the right to
contest the association's procedural standing, and of its lawsuit.
3. Also, upon the verified application of either the association or the
developer/builder alleging substantial noncompliance, then must hold a
hearing within twenty-one (21) days of the application.
a. Said hearing will be used to determine compliance of either party.
b. Should the court find that the association is in noncompliance, the
court may suspend the lawsuit's progress for up to ninety (90) days, in
order to establish compliance.
c. The court must then calendar another hearing at the end of the ninety
(90) days to review if compliance has been met.
d. Should the court find that the association is still in noncompliance,
it can choose to discuss the action as filed without prejudice or fashion
any equitable remedy that serves the interest of justice.
(1) The court may never dismiss the action with prejudice.
(2) The court must also consider the extent of the developer/builder's
compliance.
4. Should the developer/builder fail to pay the expense incurred in
the mailing and those for holding the open meeting, the court must order
it paid within thirty (30) days of its order, plus interest.

|