NEVADA - CHAPTER 40 PROCESS

Nevada enacted a pre-litigation process in 1995 and amended it in 1999 to parallel rather than precede a lawsuit. The following information will mostly pertain to complex matters, i.e. claims that have five or more homes.

1. Useful Terms

  • Appurtenance: structure, installation, facility, amenity, or other improvement that benefits residents and is not a part of the dwelling unit. These may include recreational facilities, sidewalks, and walls.
  • Claimant: residence owner or representative of a homeowner's association.
  • Complex Matter: generally means claims that involve 5 or more separate residences at the time the action is commenced.
  • Defect: conditions that materially affect the value or use of residential property in an adverse manner.
  • Dwelling Unit: any structure that is occupied as, designed, or intended to be occupied as a residence.
  • Home: structure used primarily for residential purposes.
  • Master Developer: a person who buys, sells, or develops real estate contemplating planned developments.
  • Contractor: person who
    1. Develops residences
    2. Develops a site for a residence
    3. Sells residences by himself or through agents

2. Pre-Chapter 40 Claims

The current Chapter 40 Process does not apply to construction defect claims arising on or before July 1, 1995.

3. Chapter 40 Step by Step

A. Notice to Builder

When a construction defect action is commenced, then claimant is to submit a formal written notice to the contractor that specifies in reasonable detail each defect sued upon. The notice must also include:

  1. The location of the defect and the nature and extent of injuries or damages caused by the defect. If an expert opinion was obtained regarding the defects, then a written copy must be included in the notice.
  2. Any expert opinion on the defects or injuries and damages must be based on samples from the residences or appurtenances.

The Chapter 40 Process now insulates master developers against complex suits for construction defects in planned unit developments where appurtenances were constructed on behalf of any master developer, unless:

  1. The master developer fails to disclose the identity, address, and telephone number of each contractor used to construct the appurtenance. There must be a request for such information, and 30 days to fulfill the request.
  2. After the claimant has made a good faith attempt to obtain full recovery the responsible contractors, full compensation is not made.
  3. If a court determines that a claimant cannot obtain full recovery from the contractors, or if the contractors are bankrupt, insolvent, or dissolved, the statutes of limitation are tolled against the master developer. The claimant then has one year to file an action against any master developer.

 

B. Duties and Options of the builder

After the suit is filed, the builder must then file a timely answer. In addition, written responses to the defect allegations must be made no less than 60 days prior to the initial date of mediation, unless the parties agree otherwise.

The claimant must reply to the builder's response no later than 45 days after it was mailed or constructively received. Also, no later than 30 days following the date of service of the answer, the builder and claimant must meet and confer to establish a schedule for:

  1. All reports, photos, correspondence, plans, work orders for repair and other documents or materials relating to the claims that are not privileged.
  2. Inspections of residences or appurtenances that are part of the claim to evaluate the allegations enumerated in the defect list.
  3. The time frame to perform tests to determine the nature and cause of the defects, the scope of the damages, and extent of necessary repairs. The party conducting the testing must give notice to all other parties involved.
  4. A mandated meet and confer session, which also sets forth a schedule to file claims against parties not already involved.

The claimant and builder must then settle on a mediator and proceed to mediation.

 

C. Offer by Builder

As part of the initial response to the suit, a builder must submit a written offer of settlement. The claimant may reasonably reject such an offer.

Within 60 days following the service of a summons and complaint, any settlement offer must:

  1. Be served by certified mail, return receipt requested, at claimant's last known address;
  2. Respond to each defect set forth in claimant's notice, and
  3. Describe in reasonable detail the cause of the defect, the nature and extent of damages, and method of repair.

The offers may also include:

  1. A proposal for monetary compensation;
  2. An agreement to make repairs;
  3. An agreement to have another contractor make the repairs.

The mediation process allows the builder another 60 days prior to mediation, despite the original 60 days, to submit a settlement offer. The parties may extend the time periods.

If the claimant is a part of a homeowners' association, the association shall submit any settlement offers to each member of the association within 30 days of receipt. The statute is silent as to the powers the general membership has as a result of receiving the offer.

 

D. Effect of Unreasonable Conduct

If a claimant unreasonably rejects a settlement offer made by the builder, or does not permit the builder a reasonable opportunity to make repairs pursuant to an accepted offer, and then commences a lawsuit governed by the Chapter 40 Process, the court may:

  1. Deny the claimant attorneys' fees and costs; and
  2. Award attorneys' fees and costs to the builder.

Unless the builder takes the following steps, the claimant may commence a lawsuit without further compliance with the Chapter 40 Process:

  1. Make a good faith response to claims if it asserts no liability;
  2. Make an offer of settlement;
  3. Complete the repairs specified in an accepted offer in a good and workmanlike manner;
  4. Agree to mediate or accept the appointment of a mediator; or
  5. Participate in mediation.

 

E. Response to Settlement Offer

If a builder's offer has not been accepted within 45 days of receipt, it is deemed rejected. Also, if the offer clearly notifies the claimant of the consequences for failing to respond to a settlement offer, an affidavit certifying rejection of the offer may be filed with the court.

 

F. Option to Repurchase Property

A builder may settle a claim by a written agreement to repurchase the claimant's residence. The repurchase agreement may include reimbursement for:

  1. The market value of the residence without construction defects. If the house is less than two years old, and the builder who is being sued sold the house to the claimant, then market value is the price paid by the claimant.
  2. The value for any improvements made to the property by a person other than the builder.
  3. Reasonable attorneys' fees and fees for experts; and
  4. Any costs, including costs and expenses for moving and costs, points, and fees for loans.

 

G. Curing Health or Safety Threats

A builder who receives written notice of defects that create an imminent threat to the health or safety of residential inhabitants must take reasonable steps to cure such defects as soon as is practicable. If the builder fails to take reasonable steps to cure the defect, the residence owner may fix the defect and recover any reasonable costs of repair.

If a builder reasonable believes after a good faith inspection that no health threat exists, there may be no liability for costs. However, if a building inspector employed by the governmental body with jurisdiction certifies that an imminent threat exists, the builder will be subject to damages.

 

H. Inspection of Repairs

A builder making repairs under the Chapter 40 Process is allowed to take reasonable steps to prove the repairs were made by having them inspected.

 

I. Mediation

The parties are required to select a mediator by agreement. If they cannot agree within 45 days after the claimant first selects a mediator, either party may petition for appointment. The mediator may look only at those documents or records that are necessary to conduct the mediation.

The mediation must be completed within 60 days after the matter has been submitted to the mediator, unless the parties agree to an extension. Also, both parties share the costs equally.

If the parties do not reach an agreement during mediation, or if the builder fails to pay the required fees and appear, the claimant may commence a lawsuit.

 


Contact The Miller Law Firm

[HOME PAGE] [WHAT'S NEW] [CLAIM DEVELOPMENT] [CONSUMER GUIDE] [CLIENT SERVICES] [FIRM INFORMATION]
[CONSTRUCTION DEFECTS] [UPCOMING EVENTS] [ONLINE RESOURCES] [VERDICTS & SETTLEMENTS]
[EARTHQUAKES] [ONLINE PRESS] [THE BOOK] [LAW & LEGISLATION] [CONTACT US]

© Copyright 2001 The Miller Law Firm All rights Reserved.
If you experience problems or have questions, contact us at Info@ConstructionDefects.com.