The Miller Law Firm

The Miller Law Firm
   California > Prelitigation Steps > Calderon Process7/25/2008 5:11:22 AM   

The Calderon Process


The Calderon Process is the commonly used phrase for California's Civil Code §1375 and it does not apply to all construction defect claims. The process applies to all common interest developments with 20 or more units. A common interest development in California includes a condominium project and a planned development.

Steps

1. Notice to Builder

Associations must give written notice to a builder before going ahead with an action for construction defects. Notice to the builder must include all of the following: (a) A preliminary list of defects (b) A summary of the results of a survey or questionnaire distributed to homeowners to determine the nature and extent of defects, if such a survey has been conducted or a questionnaire has been distributed. (c) Either a summary of the results of testing conducted to determine the nature and extend of defects of the actual test results, if such testing has been conducted.

2. 90-Day Settlement Period

Once the notice has been delivered to the builder, the 90-day settlement period begins, unless the association and builder agree to a longer period. Within that time, the association and builder must either attempt to settle the dispute or agree to submit to an alternative dispute resolution.

3. Notice as to Tolling Statues of Limitation

In general, when the association mails their notice, all statutory and contractual limitations are tolled against all responsible parties. Tolling occurs whether the parties are named or not. The tolling period is for 150 days, or a longer period as agreed to in writing by the association and builder.

4. Builder's Notice to Cancel Tolling

At any time during the Calderon Process, the builder may give written notice to cancel the tolling of the statute of limitations. The association is then relieved of any further obligations to satisfy the remaining requirements in the Calderon Process.

5. Builder's Request to Meet with Board of Directors

Within 25 days of the date the builder receives the association's notice, the builder may request in writing to meet and confer with the board of directors to inspect the property and conduct testing.

If the builder does not make a timely request to meet with the board of directors or to inspect and conduct testing, the association shall be relieved from any further obligations under the Calderon Process.

6. Time and Conduct of Meeting

The meeting must take place no later than 10 days from the date of builder's written request. The discussions are privileged communications and are not admissible in evidence in any civil action, unless the association and builder agree otherwise.
The meeting must be for the purpose of and cover all of the following:
(a) The nature and extent of the claimed defects.
(b) Proposed methods of repair, to the extent there is sufficient information.
(c) Proposals for submitting the dispute to alternative dispute resolution.
(d) Requests from the builder to inspect the project and conduct testing.

7. Notice to Insurers

If the builder requests a meeting with the board of directors, then the builder must deliver the association's notice to any insurers that have issued policies to the builder. The notice will impose a duty and an obligation upon the insurer.
(a) The duty imposed on the insurer is to defend the builder/insured or indemnify the insured for losses identified in the association's notice.
(b) The obligation is imposed on the insurer when the insurer receives the builder's notice. The obligation depends on the terms of the policy and whether the insurer has been served with a summons and complaint for damages.

8. Testing by Builder

If the association conducted any testing prior to when written notice was sent, then the builder must be allowed to test those same areas. Testing in these areas must be completed within 15 days from the date when the areas have been made available to test, unless the association and builder agree to a longer date. If the builder does not complete testing with in the 15 days, the association does not have to make that property available for testing. The builder is to pay for all costs for testing requested by the builder and is to restore all property tested to the condition is was prior to testing.

9. Builder's Settlement Offer and Request for Second Meeting with Board of Directors

The builder is to submit the following to the association within 30 of testing, or if no testing conducted, 30 days after the first meeting:
(a) A written request to meet with the board to discuss a settlement offer
(b) A settlement offer that gives the reasons for the terms of the offer.
(c) A statement that the builder has sufficient funds to meet the terms of the offer.
(d) A summary of testing results that were conducted to determine the defects, if testing had been conducted If the builder fails to meet the above criteria, then the association does not have to satisfy any obligations under #10-Second Meeting with Board of Directors

10. Second Meeting with Board of Directors

The board of directors is to meet with the builder 10 days after the settlement offer above has been received to discuss the terms.

11. Modifying Calderon Time Periods

At any time after the original notice is delivered to the builder, the association and builder may agree in writing to modify any other obligations in the Calderon Process.

12. Steps Upon Rejection of Offer Following Second Meeting

If the board of directors rejects the settlement offer, then the board must hold an open meeting with each member of the association. The open meeting must be held no less than 15 days before actions are taken against the builder. The board of directors must give written notice to each member no less than 15 days before the meeting specifying the following:

(a) A meeting will take place to discuss problems that may lead to filing a civil action and the time and place of the meeting.
(b) The options that are available, including:
(1) Filing of a civil action,
(2) Statement of the various alternatives.
(3) Whether payments are to be made from the use of reserve accounts, the imposition of regular assessments, or emergency assessment increases (c) The builder's settlement offer, including the explanations for the offer.
(d) The preliminary list of defects provided by the association to the builder, a list of any other documents the association gave to the builder, and information about when and where association members may inspect those documents.

13. Procedure if Association is Relieved of Second Meeting Requirement

If an association is relieved of its Calderon Process obligations because the builder has failed to meet its obligations, then the association may file an action for damages against the builder.

The action may be filed 30 days after sending written notice to each association member specifying all of the following:

(a) The preliminary defects list and any other documents the association gave to the builder, and information about when and where association members may inspect the documents.
(b) Any available options that are available to address the problems.
(c) A statement allowing for a special meeting to take place:
(1) If 5% of association members request a meeting, then a meeting shall be held within 15 days of the date notice is mailed or delivered to the members or
(2) If governing documents of the association call for a different method to call special meetings, then the statement shall inform members of that procedure.

14. Judicial Relief for Failure to Comply with Calderon Process

Judicial relief can only be sought by asserting a procedural deficiency action. This action must be filed with the court no later than 90 days after the builder's answer to the association's complaint has been served. The court will then schedule a hearing within 21 days to determine whether the association or builder has substantially complied with the Calderon Process.

If the court finds that the association did not substantially comply with the Calderon Process, then the court will give the association 90 days to establish substantial compliance. Then, if the court determines that the association did not substantially comply with the process, the court may dismiss the action without prejudice, or another remedy may be fashioned. The court may not dismiss the case without prejudice, and may take the builder's actions into consideration when fashioning a remedy.

If a court finds the builder did not pay its share of any costs, then the court shall order the builder to reimburse those costs within 30 days, with interest, and the court may award additional costs or penalties.


For more legislation information, see the California Legislation Web Site at http://www.leginfo.ca.gov.


What's New - Consumer Guide - Firm Information - Online Press
Construction Defects - Law & Legislation - Claim Development - Client Services
Upcoming Events - Verdicts & Settlements - Online Resources
Miller Publications - Disaster Relief - Construction Defect Seminars - Contact Us - Home

© Copyright 2008 The Miller Law Firm.  All rights Reserved.
If you experience problems or have questions, contact us at Info@ConstructionDefects.com.