| January 15, 1999 |
Association sends notice to Builder
of compliance with Civil Code §1375 Calderon Process
commences. |
| February 9, 1999 |
Builder request to meet with Board
of Directors is due (25 days after Builder receives
Association notice to Builder) |
| February 9, 1999 |
Builder must notify insurer of claim,
and notify Association of such notice to Builder |
| February 19, 1999 |
First Meet and Confer (10 days after
Builder's request) |
| February 20 - March 7, 1999 |
Association makes site available
for testing and inspections |
| April 6, 1999 |
Builder may submit second request
to meet, written settlement offer, statement of access
to funds and test results (30 days from inspections) |
| April 16, 1999 |
First possible date for second Meet
and Confer (10 days from Builder's request on April
7, 1999) |
| April 16, 1999 |
If Association accepts Builder's
settlement offer, process ends |
| April 16, 1999 |
If Association rejects Builder's
settlement offer, Association must give written notice
of membership meeting |
| May 1, 1999 |
First possible date of membership
(15 days after notice to membership is sent) |
| May 16, 1999 |
Lawsuit filed (15 days after open
meeting) |
| May 7, 1999 |
Statute of limitations begins to
run again (150 days from January 15, 1999, when statute
tolled) |
CONSTRUCTION
DEFECT, CONSTRUCTION LAW, CONSTRUCTION DEFECT LAW, constructiondefects,
construction defects, property, patent, latent, defect litigation,
settlement, management, trial, discovery, experts, architectural,
geotechnical, soil, structure, retaining counsel, Status of
Limitations, sub general contractor, remedies, legislation,
insurance, indicators problems, cracks For more legislation information, see the California Legislation Web Site at http://www.leginfo.ca.gov.
© Copyright 2008 The Miller Law Firm. All rights Reserved.
If you experience problems or have questions, contact us at Info@ConstructionDefects.com.
|